https://anurageros.blogspot.in/2017/09/safety-operating-procedures-required-in.html |
STANDARD OPERATING PROCEDURES : LEAK DETECTOR (VL/BL DETECTION)
1.
DRAIN
OUT THE WATER FROM THE AIRLINE . BLOW OUT DIRT AND WATER FROM THE FILTER
REGULATOR UNIT OF LD-01. CLEAN ALL THE PHOTO DIFFUSIVE SENSORS OF LD-01
2.
RESET
LD-01 BY PRESSING THE (.) DOT BUTTON ON THE TOP RIGHT CORNER OF HMI AND WAIT
TILL ‘CUC IN PROCESS MODE’ DISPLAYS. PRESS START BUTTON
3.
PUT
VL TEST CYLINDER ON THE CONVEYOR.
4.
CHECK
WHETHER THE UNIT IS REJECTING IT OR NOT. IF THE CYLINDER IS NOT GETTING
REJECTED ADJUST THE SENSITIVITY SO THAT VL CYLINDERS OF LEAKAGE ABOVE 0.5GM/HR
ARE REJECTED.
5.
CARRY
OUT THE CHECK EVERY TWO HOURS AND RECORD IT.
STANDARD OPERATING
PROCEDURES : LEAK DETECTOR (O RING LEAK DETECTION)
1.
DRAIN
OUT THE WATER FROM THE AIRLINE . BLOW OUT DIRT AND WATER FROM THE FILTER
REGULATOR UNIT OF LD-02. CLEAN ALL THE PHOTO DIFFUSIVE SENSORS OF LD-02
2.
RESET
LD-02 BY PRESSING THE (.) DOT BUTTON ON THE TOP RIGHT CORNER OF HMI AND WAIT
TILL ‘CUC IN PROCESS MODE’ DISPLAYS. PRESS START BUTTON
3.
PUT
ORL TEST CYLINDER ON THE CONVEYOR.
4.
CHECK
WHETHER THE UNIT IS REJECTING IT OR NOT. IF THE CYLINDER IS NOT GETTING
REJECTED ADJUST THE SENSITIVITY.
5.
CARRY
OUT THE CHECK EVERY TWO HOURS AND RECORD IT.
STANDARD OPERATING PROCEDURES : VALVE CHANGE WITHOUT EVACUATION
STANDARD OPERATING PROCEDURES : VALVE CHANGE WITHOUT EVACUATION
STEP1:SWITCH ON THE HYDRAULIC POWER PACK
STEP2:LOADING
1.
INTRODUCE
THE LPG CYLINDER ON THE BASE PAD (RUBBER PAD) OF THE MACHINE AND CENTER IT APPROXIMATELY
UNDER THE SEALING BELL.
2.
IN
THE START OF OPERATION, SEALING BELL & TOLL REMAIN IN ITS UPWARD POSITION.
3.
OPERAT
THE (WRENCH SHAFT LEVER) HAND VALVE DOWN POSITION FOR LOWER WRENCH SHAFT.
4.
THE
WRENCH SHAFT LOWER DOWN & ENTER IN SEALING BELL, WRENCH SHAFT HOLD NEAR THE
BALL VALVE, UNTIL BALL VALVE FULL OPEN (A PNEUMATIC ROLLER VALVE MOUNT AT
SEALING BELL STRUCTURE, THIS ROLLER VALVE PRESSED BY ALUMINIUM SLID FIX ON THE
WRENCH SHAFT STRUCTURE PORTION & MOVE UP & DOWN WITH WRENCH SHAFT &
GIVE THE SIGNAL TO THE BALL VALVE ACTUATER FOR BALL VALVE OPEN/CLOSE)
5.
AFTER
OPENING THE BALL VALVE, WRENCH SHAFT ENTERS IN THE BALL VALVE & CLOSE IT OR
SEALING BELL LEVER.
6.
OPERATE
THE (SEALING BALL LEVER) HAND LEVER VALVE DOWN POSITION FOR DOWN THE SEALING
BELL.
7.
LOWER
THE SEALING BELL UNTIL THE WRENCH IS SLIGHTLY ABOVE THE TOP OF THE CYLINDER
VALVE (WRENCH SHAFT ARRANGEMENT DOWN WITH SEALING BELL BECAUSE WRENCH SHAFT
ARRANGEMENT ATTACHED WITH BELL PORTION).
STEP 3: ALIGNMENT
1.
THIS
STEP IS CRITICAL TO THE SUCCESS OF ALL FURTHER OPERATIONS
2.
SHIFT
THE CYLINDER UNTIL THE CYLINDER VALVE IS ALLIGNED WITH THE WRENCH SOCKET.
3.
DO
NOT TILT CYLINDER TO GET THIS ALLIGNMENT.
4.
THE
FOOT RING OF THE CYLINDER MUST BE FULLY ON THE BASE PAD BEFORE ENGAGEMNT IS
ATTEMPTED.
5.
USE
THE VP RING OR BODY OF THE CYLINDER TO MOVE IT.
6.
DO
NOT INTRODUCE YOUR HAND UNDER THE SEALING BELL.
7.
LOOK
FROM TWO ORTHOGONAL POSITIONS TO ENSURE PROPER AXIAL ALLIGNMENT.
8.
LOWER
THE SEALING BELL FURTHER SO THAT THE SOCKET ENGAGES THE VALVE.
9.
LOWER
THE SEALING BELL FURTHER STILL UNTIL THE FACE CONTACTS, THE LPG CYLINDER &
PRESSES DOWN FIRMLY ON IT.
10.
LEAVE
THE SEALING BELL CONTROL LEVER.
11.
YOU
ARE NOW READY TO UNSCREW THE CYLINDER VALVE.
STEP4:UNSCREWING
1.
SHIFT
THE UNSCREW CONTROL LEVER AND HOLD IT UP TO ROTATE THE WRENCH ANTICLOCKWISE.
2.
AS
THE VALVE UNSCREWS THE WRENCH SHAFT WILL CREEP UP AUTOMATICALY.
3.
WHEN THE VALVE IS FULLY UNSCREWED .THE WRENCH
SHAFT WILL STOP CREEPING UP.
4.
KEEP
THE UNSCREWING MOTION ON AND SIMULTANEOUSLY SHIFT THE WRENCH SLIDE LEVEL TO THE
UP POSITION.
5.
AS
SOON AS THE WRENCH LIFTS 40 TO 50 MM RELESE THE UNSCREW CONTROL LEVELBUT KEEP
WRENCH TOOL VALVE IN THE UP POSITION TO CONTINUE LIFTING THE SHAFT.
6.
LPG
PRESSRE RISE IN THE PRESSURE GAUGE. PRESSURE GAUGE MOUNTS ON THE SEAL BELL
7.
WHEN
THE WRENCH SHAFT WITH SC VALVE CROSSED THE BALL VALVE 20MM (AFTER LIFTING 320
MM FROM SEALING BELL LOWER PORTION), A PNEUMATIC ROLLER LEVER VALVE GIVES THE
SIGNAL TO BALL VALVE FOR CLOSING.WRENCH SHAFT WILL LIFT OUT OF THE SEALING BELL
WITH THE VALVE ALLOW IT TO TRAVEL FULLY UP.
STEP5: SCREWING
1.
AFTER
REPLACING THE NEW SC VALVE ON THE WRENCH SOCKET, PRESS WRENCH LEVER DOWN
POSITION TO MOVE THE WRENCH SHAFT IT’S DOWN POSITION.
2.
THE
WRENCH SHAFT ENTER IN THE SEALING AREA & STOP NEAR THE BALL VALVE (A
PNEUMATIC ROLER GIVE THE SIGNAL FOR OPEN THE BALL VALVE).
3.
AFTER
FULLY OPEN THE BALL VALVE WRENCH SHAFT MOVE DOWN POSITION.
4.
NOW
SHIFT THE SCREW LEVER FOR SCREWINING TO ROTATE THE WRENCH SHAFTCLOCKWISE.
5.
THE
WRENCH SHAFT DOWN MOVE SLIGHTLY. AFTER VALVE SCREWING THE WRENCH SHAFT WILL
STOP AUTOMATICALY.
6.
YOU
HAVE NOW SCREWED THE NEW VALVE ON CYLINDER.
7.
NOW
RELEASE THE SCREW LEVER STOP POSITION & SHIFT THE SEALING BELL LEVER IT’S
UP POSITION.
8.
NOW
PRIMARY VENT IS ON FOR LPG PRESSURE VENTILATION IN COLD FLAIR.
9.
AFTER
COMPLETE THE LPG FLAIR.SEALING BELL LIFT UPPER SIDE.
10.
BELL
WILL NOT LIFT UP IF THE PRESSURE INSIDE THE BELL IS NOT 0 TO 0.5GM FOR THIS
SAFETY INTERLOCK, TWO PNEUMATIC PRESSURE SWITCHES CONNECTED WITH SEALING BELL.
WHEN IT GIVES THE SIGNAL FOR COMPLETE FLARING SEALING BELL WILL LIFT OTHERWISE
IT WILL NOT LIFT UP.
STEP6: SHUT DOWN PROCEDURE END OF THE DAY
SHIFT.
1.
THE
END OF THE DAY THE MACHIN SHOULD BE SHUT DOWN IN THE IN THE CORRECT CONDITION.
2.
THERE
SHOULD BE NO CYLINDERS IN THE MACHINE.
3.
MOVE
THE SEALING BELL DOWN TO ITS LOWEST POSITION AND LEAVE THE CONTROL LEVEL IN
NATURAL.
4.
MOVE
THE WRENCH SLIDE DOWN TO ITS LOWEST POSITION AND LEAVE THE CONTROL LEVER IN THE
SHUTDOWN POSITION.
5.
SWITCH
OFF THE HYDRAULIC POWER PACK.
6.
TURN
OFF THE AIR SUPPLY
NOTE: PROBLEMS DURING
SCREWING/UNSCREWING
1.
IN
THE CASE VALVE NOT COMPLETE THE SCREW/UNSCREW, VALVE DROP OUT THE WRENCH IN THE
SEALING BELL AREA.
2.
IN
SUCH CASE THE LPG IN THE CYLINDER MUST BE VENTED VIA SECONDARY VENT BEFORE THE
SEALING BELL CAN BE LIFTED.
3.
A
LPG VENTILATION PIPELINE ATTACHED WITH PRIMARY & AND SECONDARY VENT LINE
FOR REMOVING THE LPG PRESSURE FOR COLD FLAIR
INTERLOCKS:
1.
AN
INTERLOCK PROVIDED FOR CHECKING THE BALL VALVE CLOSED POSITION, THE TOLL SHAFT
UPWARD POSITION STOP IN SEALING AREA TILL THE BALL VALVE FULLY CLOSED SIGNAL.
2.
AN
INTERLOCK PROVIDED FOR CHECKING THE BALL VALVE OPEN POSITION THE WRENCH SHAFT
DOWNWARD POSITION STOP IN SEALING AREA TILL THE BALL VALVE FULLY OPEN SIGNAL.
3.
THE
PRESSURE SWITCH USED IN BELL. THE SEALING BELL LIFT UP,WHEN SEALING BELL INSIDE
PRESSURE IS NILL.
4.
A
PRESSURE RELEASE VALVE PROVIDED IN POWER PACK FOR AVOIDING THE OVER
PRESSURE.THIS VALVE RELESE THE EXTRA OIL PRESSURE IN RETURN LINE.
STANDARD OPERATING PROCEDURES :
AUTOMATIC VALVE TESTING SYSTEM (ELECTRONIC TYPE)
1.
NORMALLY
WHEN THE MACHINE IS ON AND THERE IS NO TESTING GOING ON, THEN ‘INSPECTION OFF’ WILL APPEAR ON THE GLASS WINDOW SCREEN.
2.
WHEN
A CYLINDER COMES FOR TESTING AND DURING TESTING ‘INSPECTION ON’ WILL APPEAR ON
THE GLASS WINDOW SCREEN.
3.
ONCE
THE TESTING IS COMPLETED AND THE CYLINDER IS OK THEN ‘OK’ WILL APPEAR ON THE
GLASS WINDOW SCREEN.
4.
DURING
TESTING IF THE CYLINDER IS REJECTED FOR PIN LEAK OR ‘O’ RING DEFECT THEN ‘REJECTS’
WILL APPEAR ON THE GLASS WINDOW SCREEN.
DO’S AND DON’T’S
1.
DO
NOT CHANGE THE POSITION OF SENSORS.
2.
DO
NOT CHANGE THE AIR PRESSURE FROM THE MAIN FRL UNIT WHICH IS SET NORMALLY AT
5KG/CM^2.
3.
DO
NOT CHANGE THE PRESSURE SETTING OF THE PRESSURE REGULATOR PROVIDED INSIDE THE
CONTROL PANEL.
4.
DO
NOT START THE MACHINE WITHOUT AS MUCH AIR AS IT MAY DAMAGE THE COMPONENTS.
5.
DO
NOT ALLOW CYLINDERS TO MOVE ON BELLY FOR TESTING.
6.
DO
NOT OPERATE FUNCTION KEYS DURING TESTING. (F1, F2, F3…)
7.
ALWAYS
KEEP THE INLET AIR PRESSURE TO THE SYSTEM TO THE CORRECT VALUE.
8.
ALWAYS
SUPPLY 230V AC TO THE MACHINE THROUGH UPS.
9.
CHECK
FOR ANY AIR LEAKAGE IN THE SYSTEM, IF FOUND INFORM OFFICER IN CHARGE.
10.
WITH
THE POWER ON DO NOT OPEN THE FLAME PROOF JUNCTION BOX OR TERMINAL JUNCTION
BOXES PROVIDED AT THE BACK OF THE CONTROL PANEL.
11.
WITH
THE POWER ON DO NOT TAMPER ANY ELECTRICAL CONNECTION.
FUNCTION PUSH BUTTONS IN THE CONTROL
PANEL
THESE PUSH BUTTONS ARE TO BE
OPERATED ONLY WHEN THE MACHINE IS NOT IN RUNNING CONDITION
F1 WHEN PRESSED WILL SHOW THE NUMBER
OF CYLINDERS TESTED IN THE MACHINE
F2 WHEN PRESSED WILL SHOW THE TEST
TIME
F3 WHEN PRESSED WILL SHOW SELECT PR
( TO SELECT THE TEST ACCURACY OF THE MACHINE VIZ 0.5,0.75,1.0)
F4 WHEN PRESSED WILL SHOW PREVIOUS CYLINDER TESTED
LEAKAGE VALUE IN TERMS OF CURRENT
UP TO BE OPERATED ONLY TO INCREASE
THE F2 BUTTON VALUE OR F3 BUTTON VALUE
DOWN TO BE OPERATED ONLY TO DECREASE
THE F2 BUTTON VALUE OR F3 BUTTON VALUE
RESET WHEN PRESSED WILL ERASE THE F1
VALUE
M-RESET TO BE OPERATED ONLY WHEN
THE SUPPLY AIR PRESSURE FALLS BELOW THE
SET VALUE AND ‘PNEUMATIC LOW’ APPEARS ON HMI
ReplyDeleteVery Useful information Thank you!!
TWB_’s team of technical documentation specialists, illustrators and production staff create documentation to meet the North Sea & American Petroleum Institute (API)
standards. TWB_ produces Manuals, CBTs, IETMs, 2D & 3D drawings and write in STE as well as translate into multiple European languages & Korean & Japanese. TWB_ has
a large footprint of customers including Averda &Amaco in the Middle East and Tatsuno, Tokhiem, Samsung Engineering in the Far East
Technical Manuals | Operating Procedures | Emergency Procedures Manuals | Maintenance Manuals | Training Package