Skip to main content

Safety Operating Procedures required in an LPG plant

https://anurageros.blogspot.in/2017/09/safety-operating-procedures-required-in.html


STANDARD OPERATING PROCEDURES : LEAK DETECTOR (VL/BL DETECTION)

1.       DRAIN OUT THE WATER FROM THE AIRLINE . BLOW OUT DIRT AND WATER FROM THE FILTER REGULATOR UNIT OF LD-01. CLEAN ALL THE PHOTO DIFFUSIVE SENSORS OF LD-01
2.       RESET LD-01 BY PRESSING THE (.) DOT BUTTON ON THE TOP RIGHT CORNER OF HMI AND WAIT TILL ‘CUC IN PROCESS MODE’ DISPLAYS. PRESS START BUTTON
3.       PUT VL TEST CYLINDER ON THE CONVEYOR.
4.       CHECK WHETHER THE UNIT IS REJECTING IT OR NOT. IF THE CYLINDER IS NOT GETTING REJECTED ADJUST THE SENSITIVITY SO THAT VL CYLINDERS OF LEAKAGE ABOVE 0.5GM/HR ARE REJECTED.
5.       CARRY OUT THE CHECK EVERY TWO HOURS AND RECORD IT.

STANDARD OPERATING PROCEDURES : LEAK DETECTOR (O RING LEAK DETECTION)

1.       DRAIN OUT THE WATER FROM THE AIRLINE . BLOW OUT DIRT AND WATER FROM THE FILTER REGULATOR UNIT OF LD-02. CLEAN ALL THE PHOTO DIFFUSIVE SENSORS OF LD-02
2.       RESET LD-02 BY PRESSING THE (.) DOT BUTTON ON THE TOP RIGHT CORNER OF HMI AND WAIT TILL ‘CUC IN PROCESS MODE’ DISPLAYS. PRESS START BUTTON
3.       PUT ORL TEST CYLINDER ON THE CONVEYOR.
4.       CHECK WHETHER THE UNIT IS REJECTING IT OR NOT. IF THE CYLINDER IS NOT GETTING REJECTED ADJUST THE SENSITIVITY.
5.       CARRY OUT THE CHECK EVERY TWO HOURS AND RECORD IT.
STANDARD OPERATING PROCEDURES : VALVE CHANGE WITHOUT EVACUATION

STEP1:SWITCH ON THE HYDRAULIC POWER PACK
STEP2:LOADING
1.       INTRODUCE THE LPG CYLINDER ON THE BASE PAD (RUBBER PAD) OF THE MACHINE AND CENTER IT APPROXIMATELY UNDER THE SEALING BELL.
2.       IN THE START OF OPERATION, SEALING BELL & TOLL REMAIN IN ITS UPWARD POSITION.
3.       OPERAT THE (WRENCH SHAFT LEVER) HAND VALVE DOWN POSITION FOR LOWER WRENCH SHAFT.
4.       THE WRENCH SHAFT LOWER DOWN & ENTER IN SEALING BELL, WRENCH SHAFT HOLD NEAR THE BALL VALVE, UNTIL BALL VALVE FULL OPEN (A PNEUMATIC ROLLER VALVE MOUNT AT SEALING BELL STRUCTURE, THIS ROLLER VALVE PRESSED BY ALUMINIUM SLID FIX ON THE WRENCH SHAFT STRUCTURE PORTION & MOVE UP & DOWN WITH WRENCH SHAFT & GIVE THE SIGNAL TO THE BALL VALVE ACTUATER FOR BALL VALVE OPEN/CLOSE)
5.       AFTER OPENING THE BALL VALVE, WRENCH SHAFT ENTERS IN THE BALL VALVE & CLOSE IT OR SEALING BELL LEVER.
6.       OPERATE THE (SEALING BALL LEVER) HAND LEVER VALVE DOWN POSITION FOR DOWN THE SEALING BELL.
7.       LOWER THE SEALING BELL UNTIL THE WRENCH IS SLIGHTLY ABOVE THE TOP OF THE CYLINDER VALVE (WRENCH SHAFT ARRANGEMENT DOWN WITH SEALING BELL BECAUSE WRENCH SHAFT ARRANGEMENT ATTACHED WITH BELL PORTION).

               STEP 3: ALIGNMENT
1.       THIS STEP IS CRITICAL TO THE SUCCESS OF ALL FURTHER OPERATIONS
2.       SHIFT THE CYLINDER UNTIL THE CYLINDER VALVE IS ALLIGNED WITH THE WRENCH SOCKET.
3.       DO NOT TILT CYLINDER TO GET THIS ALLIGNMENT.
4.       THE FOOT RING OF THE CYLINDER MUST BE FULLY ON THE BASE PAD BEFORE ENGAGEMNT IS ATTEMPTED.
5.       USE THE VP RING OR BODY OF THE CYLINDER TO MOVE IT.
6.       DO NOT INTRODUCE YOUR HAND UNDER THE SEALING BELL.
7.       LOOK FROM TWO ORTHOGONAL POSITIONS TO ENSURE PROPER AXIAL ALLIGNMENT.
8.       LOWER THE SEALING BELL FURTHER SO THAT THE SOCKET ENGAGES THE VALVE.
9.       LOWER THE SEALING BELL FURTHER STILL UNTIL THE FACE CONTACTS, THE LPG CYLINDER & PRESSES DOWN FIRMLY ON IT.
10.   LEAVE THE SEALING BELL CONTROL LEVER.
11.   YOU ARE NOW READY TO UNSCREW THE CYLINDER VALVE.



STEP4:UNSCREWING     
1.       SHIFT THE UNSCREW CONTROL LEVER AND HOLD IT UP TO ROTATE THE WRENCH ANTICLOCKWISE.
2.       AS THE VALVE UNSCREWS THE WRENCH SHAFT WILL CREEP UP AUTOMATICALY.
3.        WHEN THE VALVE IS FULLY UNSCREWED .THE WRENCH SHAFT WILL STOP CREEPING UP.
4.       KEEP THE UNSCREWING MOTION ON AND SIMULTANEOUSLY SHIFT THE WRENCH SLIDE LEVEL TO THE UP POSITION.
5.       AS SOON AS THE WRENCH LIFTS 40 TO 50 MM RELESE THE UNSCREW CONTROL LEVELBUT KEEP WRENCH TOOL VALVE IN THE UP POSITION TO CONTINUE LIFTING THE SHAFT.
6.       LPG PRESSRE RISE IN THE PRESSURE GAUGE. PRESSURE GAUGE MOUNTS ON THE SEAL BELL
7.       WHEN THE WRENCH SHAFT WITH SC VALVE CROSSED THE BALL VALVE 20MM (AFTER LIFTING 320 MM FROM SEALING BELL LOWER PORTION), A PNEUMATIC ROLLER LEVER VALVE GIVES THE SIGNAL TO BALL VALVE FOR CLOSING.WRENCH SHAFT WILL LIFT OUT OF THE SEALING BELL WITH THE VALVE ALLOW IT TO TRAVEL FULLY UP.

STEP5: SCREWING
1.       AFTER REPLACING THE NEW SC VALVE ON THE WRENCH SOCKET, PRESS WRENCH LEVER DOWN POSITION TO MOVE THE WRENCH SHAFT IT’S DOWN POSITION.
2.       THE WRENCH SHAFT ENTER IN THE SEALING AREA & STOP NEAR THE BALL VALVE (A PNEUMATIC ROLER GIVE THE SIGNAL FOR OPEN THE BALL VALVE).
3.       AFTER FULLY OPEN THE BALL VALVE WRENCH SHAFT MOVE DOWN POSITION.
4.       NOW SHIFT THE SCREW LEVER FOR SCREWINING TO ROTATE THE WRENCH SHAFTCLOCKWISE.
5.       THE WRENCH SHAFT DOWN MOVE SLIGHTLY. AFTER VALVE SCREWING THE WRENCH SHAFT WILL STOP AUTOMATICALY.
6.       YOU HAVE NOW SCREWED THE NEW VALVE ON CYLINDER.
7.       NOW RELEASE THE SCREW LEVER STOP POSITION & SHIFT THE SEALING BELL LEVER IT’S UP POSITION.
8.       NOW PRIMARY VENT IS ON FOR LPG PRESSURE VENTILATION IN COLD FLAIR.
9.       AFTER COMPLETE THE LPG FLAIR.SEALING BELL LIFT UPPER SIDE.
10.   BELL WILL NOT LIFT UP IF THE PRESSURE INSIDE THE BELL IS NOT 0 TO 0.5GM FOR THIS SAFETY INTERLOCK, TWO PNEUMATIC PRESSURE SWITCHES CONNECTED WITH SEALING BELL. WHEN IT GIVES THE SIGNAL FOR COMPLETE FLARING SEALING BELL WILL LIFT OTHERWISE IT WILL NOT LIFT UP.

STEP6: SHUT DOWN PROCEDURE END OF THE DAY SHIFT.
1.       THE END OF THE DAY THE MACHIN SHOULD BE SHUT DOWN IN THE IN THE CORRECT CONDITION.
2.       THERE SHOULD BE NO CYLINDERS IN THE MACHINE.
3.       MOVE THE SEALING BELL DOWN TO ITS LOWEST POSITION AND LEAVE THE CONTROL LEVEL IN NATURAL.
4.       MOVE THE WRENCH SLIDE DOWN TO ITS LOWEST POSITION AND LEAVE THE CONTROL LEVER IN THE SHUTDOWN POSITION.
5.       SWITCH OFF THE HYDRAULIC POWER PACK.
6.       TURN OFF THE AIR SUPPLY

               NOTE: PROBLEMS DURING SCREWING/UNSCREWING
1.       IN THE CASE VALVE NOT COMPLETE THE SCREW/UNSCREW, VALVE DROP OUT THE WRENCH IN THE SEALING BELL AREA.
2.       IN SUCH CASE THE LPG IN THE CYLINDER MUST BE VENTED VIA SECONDARY VENT BEFORE THE SEALING BELL CAN BE LIFTED.
3.       A LPG VENTILATION PIPELINE ATTACHED WITH PRIMARY & AND SECONDARY VENT LINE FOR REMOVING THE LPG PRESSURE FOR COLD FLAIR

               INTERLOCKS:
1.       AN INTERLOCK PROVIDED FOR CHECKING THE BALL VALVE CLOSED POSITION, THE TOLL SHAFT UPWARD POSITION STOP IN SEALING AREA TILL THE BALL VALVE FULLY CLOSED SIGNAL.
2.       AN INTERLOCK PROVIDED FOR CHECKING THE BALL VALVE OPEN POSITION THE WRENCH SHAFT DOWNWARD POSITION STOP IN SEALING AREA TILL THE BALL VALVE FULLY OPEN SIGNAL.
3.       THE PRESSURE SWITCH USED IN BELL. THE SEALING BELL LIFT UP,WHEN SEALING BELL INSIDE PRESSURE IS NILL.
4.       A PRESSURE RELEASE VALVE PROVIDED IN POWER PACK FOR AVOIDING THE OVER PRESSURE.THIS VALVE RELESE THE EXTRA OIL PRESSURE IN RETURN LINE.
 STANDARD OPERATING PROCEDURES : AUTOMATIC VALVE TESTING SYSTEM (ELECTRONIC TYPE)

1.       NORMALLY WHEN THE MACHINE IS ON AND THERE IS NO TESTING GOING ON, THEN ‘INSPECTION OFF’  WILL  APPEAR ON THE GLASS WINDOW SCREEN.
2.       WHEN A CYLINDER COMES FOR TESTING AND DURING TESTING ‘INSPECTION ON’ WILL APPEAR ON THE GLASS WINDOW SCREEN.
3.       ONCE THE TESTING IS COMPLETED AND THE CYLINDER IS OK THEN ‘OK’ WILL APPEAR ON THE GLASS WINDOW SCREEN.
4.       DURING TESTING IF THE CYLINDER IS REJECTED FOR PIN LEAK OR ‘O’ RING DEFECT THEN ‘REJECTS’ WILL APPEAR ON THE GLASS WINDOW SCREEN.

DO’S AND DON’T’S

1.       DO NOT CHANGE THE POSITION OF SENSORS.
2.       DO NOT CHANGE THE AIR PRESSURE FROM THE MAIN FRL UNIT WHICH IS SET NORMALLY AT 5KG/CM^2.
3.       DO NOT CHANGE THE PRESSURE SETTING OF THE PRESSURE REGULATOR PROVIDED INSIDE THE CONTROL PANEL.
4.       DO NOT START THE MACHINE WITHOUT AS MUCH AIR AS IT MAY DAMAGE THE COMPONENTS.
5.       DO NOT ALLOW CYLINDERS TO MOVE ON BELLY FOR TESTING.
6.       DO NOT OPERATE FUNCTION KEYS DURING TESTING. (F1, F2, F3…)
7.       ALWAYS KEEP THE INLET AIR PRESSURE TO THE SYSTEM TO THE CORRECT VALUE.
8.       ALWAYS SUPPLY 230V AC TO THE MACHINE THROUGH UPS.
9.       CHECK FOR ANY AIR LEAKAGE IN THE SYSTEM, IF FOUND INFORM OFFICER IN CHARGE.
10.   WITH THE POWER ON DO NOT OPEN THE FLAME PROOF JUNCTION BOX OR TERMINAL JUNCTION BOXES PROVIDED AT THE BACK OF THE CONTROL PANEL.
11.   WITH THE POWER ON DO NOT TAMPER ANY ELECTRICAL CONNECTION.

FUNCTION PUSH BUTTONS IN THE CONTROL PANEL

THESE PUSH BUTTONS ARE TO BE OPERATED ONLY WHEN THE MACHINE IS NOT IN RUNNING CONDITION
F1 WHEN PRESSED WILL SHOW THE NUMBER OF CYLINDERS TESTED IN THE MACHINE
F2 WHEN PRESSED WILL SHOW THE TEST TIME
F3 WHEN PRESSED WILL SHOW SELECT PR ( TO SELECT THE TEST ACCURACY OF THE MACHINE VIZ 0.5,0.75,1.0)
F4 WHEN  PRESSED WILL SHOW PREVIOUS CYLINDER TESTED LEAKAGE VALUE IN TERMS OF CURRENT
UP TO BE OPERATED ONLY TO INCREASE THE F2 BUTTON VALUE OR F3 BUTTON VALUE
DOWN TO BE OPERATED ONLY TO DECREASE THE F2 BUTTON VALUE OR F3 BUTTON VALUE
RESET WHEN PRESSED WILL ERASE THE F1 VALUE
M-RESET TO BE OPERATED ONLY WHEN THE  SUPPLY AIR PRESSURE FALLS BELOW THE SET VALUE AND ‘PNEUMATIC LOW’ APPEARS ON HMI


Comments


  1. Very Useful information Thank you!!
    TWB_’s team of technical documentation specialists, illustrators and production staff create documentation to meet the North Sea & American Petroleum Institute (API)

    standards. TWB_ produces Manuals, CBTs, IETMs, 2D & 3D drawings and write in STE as well as translate into multiple European languages & Korean & Japanese. TWB_ has

    a large footprint of customers including Averda &Amaco in the Middle East and Tatsuno, Tokhiem, Samsung Engineering in the Far East
    Technical Manuals | Operating Procedures | Emergency Procedures Manuals | Maintenance Manuals | Training Package

    ReplyDelete

Post a Comment

Popular posts from this blog

Koodallur Mana: Heritageous mansion

K oodallur Mana is in Palakkad district in Kerala. After catching a Guruvayur bus it will lead you to a place named ' Vavannur' . Kudallur Mana is 1km nearby from that area. The name ' Koodal' came from the union of two rivers Bharatpuzha and Thoothapuzha . Koodallur mana exists on the banks of those two rivers. It is the only place where there Saint Pathanjali's dedication exist.  http://anurageros.blogspot.in/2017/10/koodallur-mana-heritageous-mansion.html Mana has experienced over 14 generations. The malayali Namboodiris of the Mana are the clans of Agnihotri . Once sanskrit was the language of litigation in Mana.  The art works found on the front door and roof above the threshold are really surprising. Koodallur Mana is 450years old. Two ponds which have steps are built still exist here. Mana owns 5 wells. There were two storage bin houses and they are broken now. Non namboodiri students where studied by staying there at the bin houses. Serpent

DNB CET - SS 2018

Diplomate of National Board Centralised Entrance Test- Super Speciality, is conducted by National Board of examinations for the entry of candidates for Doctor of Medicine or Master of surgery degree and other Super Speciality courses. Also it gives admission to various super speciality courses. These super speciality courses have a duration of 3 years and gives entrance to various NBE affiliated Medical colleges and other Institutions. DNB CET- SS are conducted twice in an year, in January and in July. This entrance examination is of national level. The applicants can write any one of the above exams and can join the courses. Eligibility criteria for Applying DNB CET – SS 2018 Applicants must hold the MBBS and MD/MS degree recognized by the Medical council of India. Appearing candidates can also apply, but they must possess their Pass certificates by 31 st December 2017. Otherwise applicants would be rejected from DNB CET SS 2018. Along with this, applicants should

Machining Processes & Machine Tool operations MCQ Mechanical

1. The cutting edge of the tool is perpendicular to the direction of tool travel in                                   A. Orthogonal cutting of metals  B. Oblique cutting of metals C. Both a and b D. None of these Ans: Orthogonal cutting of metals 2. The cutting edge of the tool is inclined at an angle less than 90 to the direction of tool travel in A. Orthogonal cutting of metals B. Oblique cutting of metals C. Both a and b D. None of these Ans: Oblique cutting of metals 3. Two components of the cutting forces which are perpendicular acting on the cutting tool in A. Orthogonal cutting of metals B. Oblique cutting of metals C. Both a and b D. None of these Ans: Orthogonal cutting of metals 4. Orthogonal cutting systems are also known as A. One dimesional cutting system B. Two dimensional cutting system C. Three dimensional cutting system D. none of these Ans: Two dimensional cutting system 5. Three components of the cutting forces which